This is the start of a weekly update of plans for the week, this week -
- Plans - finalize plans for common areas and rooms and finish structual plans
- Water tank - finish plaster of the tank and set a concrete cover for it
- Common areas - put all columns in and if we manage get the 1st floor floor in place (plans are to have a drink on Jake's birthday - 19th of May in the future pool side bar)
- Room blocks - land clearance and preparance for columns
- Loki Guide - Do up new text for the Loki Guide for Mancora
- Website - update the Mancora section to have full information about Mancora, the work and plans
We got some new fancy machinery including a 24" chromed vibrator, so the workers are all excited about trying their new toys.